1、0 24 April 10 First IssueRev Date Description of Revision Checked ApprovedDocument No: SWI-0422Project No: MH0046Revision: 0Date : 2010-04-24AFRICAN MINERALS LTD Page No: 1SAFE WORK INSTRUCTIONSWI-0422INSPECTION Plan drawings Specifications of all lifting equipment Crane type Positioning of cranes N
2、ames and positions of all personnel Methods of communicationAll significant lift studies and supporting information are to be verified and signed by a competent person.Significant lift studies shall form a part of any supporting Job Safety Analysis and shall be clearly communicated to all members of the lifting crew.4. REFERENCESAS 2550 .1 Cranes Safe Use5. ATTACHMENTSSWI-F0422A Rigging RegisterSWI-F0422B Lifting Gear Safety Checklist