1、一、名词解释(5*2=10)PMI, Project Management Institute, 美国项目管理学会PMP, Project Management Professional, 项目管理专业人员认证PMBOK, Project Management Body of Knowledge, 项目管理知识体系PLC, project life cycle, 项目生命周期RFP, Request for proposal, 需求建议书WBS, Work Breakdown Structure, 工作分解结构CPM, Critical path method, 关键路径法PERT, Proj
2、ect Evaluation and Review Technique, 计划评审技术AOA, Activity-On-Arrow, 双代号网络图法AON, Activity-on-node, 单代号网络图CPI, Cost Performance Index, 成本绩效指数 (挣值(EV)/实际成本(AC)RAM, Responsibility Assignment Matrix, 职责分配矩阵P&L, Profit and loss 损益VAT, value-added tax, 加值税、增值税QA, Quality Assurance, 质量保障二、填空题(5*2=10) 。1. A p
3、roject is an endeavour to accomplish a specific objective through a unique set of interrelated tasks and the effective utilization of resources. 1.项目是努力完成一个特定的目标,通过一套独特的相互关联的任务和资源的有效利用。2. A project manager is responsible for planning the work and then work the plan.项目经理负责规划工作,然后工作计划。3. The project l
4、ife cycle has four phases: initiating, planning, performing, and closing the project.项目生命周期有四个阶段 启动、 规划、 执行和结束项目。4. Project selection involves evaluating potential projects and then deciding which should move forward to be implemented.项目选择涉及潜在项目评估,然后决定,应该向前来实施。5. WBS facilitates evaluation of cost,
5、time, and technical performance of the organization on a project. WBS 促进评估的成本、 时间和上一个项目组织的技术性能。6. The project network is developed from the information collected for the WBS and is a graphic flow chart of the project job plan. 项目开发从 WBS 收集的信息和网络是一个图形的流程图的项目工作计划。7. In the context of projects, risk is
6、 an uncertain event and condition that, if it occurs, has a positive and negative effect on project objectives. 在项目范围内,风险是不确定的事件和条件,如果它发生,已经对项目目标的积极和消极的影响。8. Milestones are significant project events that mark major accomplishments. 里程碑是重大项目事件标记的主要成就。9. Two important factors affecting recruitment ar
7、e the importance of the project and the management structure being used to complete the project.有两个重要影响因素招聘有项目和管理结构被用来完成这项工程的重要性10. The most common method for shortening project time is to assign additional staff and equipment to activities.最常用的方法,缩短项目时间是将额外的工作人员和设备分配给活动三选择题(15*2=30 )1. Communicatio
8、ns is best described as:A. an exchange of information.B. providing written or oral directions.C. consists of senders and receiversD. effective listening.E. All of the aboveANS: E2. The following types of costs are relevant to making a financial decision except:A. opportunity costsB. direct costsC. s
9、unk costD. unavoidable costsE. None of the aboveANS: C3. Time management is the allocation of time in a projects life cycle through the process of:A. PlanningB. Estimating.C. Scheduling.D. ControllingE. All of the above.ANS: E4. A project element which lies between two events is called: 位于两个事件之间的项目元
10、素被称为A. An activity.B. A critical path method.C. A slack milestone.D. A timing slot.E. A calendar completion point.ANS: A5. A comprehensive definition of scope management would be: 一个全面的定义的范围管理将是A. Managing a project in terms of its objective through the concept, development, implementation, and term
11、ination phases of a project.管理项目以及项目的概念、 发展、 实施和终止阶段通过其目的。B. Approval of the scope baseline.C. Approval of the detailed project charter.D. Configuration control.E. Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.ANS: A6. Pure
12、 Risk differs from Business Risks because Pure Risks _ .A. include chances of both profit or loss associated with the business.B. include chances of loss and no chances for profit associated with the business. 包括丢失的可能性和相关业务的利润没有机会C. must incur personal loss with business liability. 必须与业务责任招致个人损失。D.
13、must incur business liability associated with loss of pure profit.E. B and CANS: BANS: D7. The most common types of schedules are Gantt charts, milestone charts, line of balance, and:A. Networks.B. Time phased events.C. Calendar integrated activities.D. A and C only.E. B and C only.ANS: A8. In prepa
14、ring a good project definition, experienced project managers will:A. Concentrate mainly on the end product rather than costs or benefits. These come later.B. Realize that only the “tip of the iceberg“ may be showing. As a project manager, you must get beneath it.C. Understand that a project definiti
15、on/plan is a dynamic rather than static tool, and thus subject to change.D. Try to convert objectives into quantifiable terms.E. All of the aboveANS: E9. Since risk is associated with most projects, the best course of action is to:A. cover all project risks by buying appropriate insuranceB. ignore t
16、he risks, since nothing can be done about them and move forward with the project in an expeditious manner.C. avoid projects with clear and present risksD. eliminate all known risks prior to the execution phase of the projectE. identify various risks and implement actions to mitigate their potential
17、impactANS: E10. Risk management allows the project manager and the project team to:A. eliminate most risks during the planning phase of the projectB. identify project risksC. identify impacts of various risksD. plan suitable responsesE. B, C and D onlyANS: E11. Which of the following types of cost a
18、re relevant to making financial decisions:A. sunk costB. opportunity costC. material costD. A and C onlyE. B and C onlyANS: E12. Which of the following is often overlooked in achieving effective communication?A. speaking clearlyB. listeningC. interpretingD. maintaining eye contactE. manipulating the
19、 conversationANS: B13. The highest degrees of project risk and uncertainty are associated with the following phase of the project:A. conceptualB. executionC. cut-overD. post project evaluationE. A and D onlyANS: A14. The auditing function that provides feedback about the quality of output is referre
20、d to as:A. quality control.B. quality planning.C. quality assurance.D. quality improvementE. All of the above.ANS: C15. The sending or conveying of information from one place to another is the process ofA. NetworkingB. TransmittingC. InteractingD. PromotingE. InterfacingANS: B16. Project life cycles
21、 provide a better means of measurement of progress and control. The four phases of a project are conceptual development,_, _, and _.A. Preliminary planning, detail planning, closeoutB. Implementation, reporting, terminationC. Development, implementation, terminationD. Execution, reporting, finishing
22、E. Implementation, termination, post-audit reviewANS: C17. All of the following are categories of a milestone in a schedule except:A. End date.B. Contract dates.C. Key events scheduled.D. Imposed dates.E. Task duration.ANS: E18. Uncertainty refers to a situation where:A. the outcomes are known but t
23、heir probabilities are highB. the outcomes and their probabilities are knownC. neither the outcomes nor their probabilities are knownD. states of nature can change at any timeE. probabilities of various states of nature can change at any timeANS: C19. Excessive flexibility in specifying requirements
24、 will _ the likelihood of time overruns.A. Reduce.B. Eliminate.C. DoubleD. IncreaseE. Not affectANS: D20. Which of the following is closet to Demings definition of Quality:A. conformance to requirements.B. fitness for use.C. continuous improvement of products and services.D. customer focus.E. All of
25、 the above.ANS: C21. The key purpose of project control is to:A. Plan ahead for uncertainties.B. Generate status reports.C. Keep the project on track.D. Develop the project road map.E. All of the above.ANS: C22. Which of the following constitute Jurans “quality trilogy“:A. planning, inspection, cont
26、rol.B. planning, improvement, control.C. planning, organization, control.D. product, price, customer.E. design, build, deliver.ANS: B23. Most project (and non-project) managers prefer _ communications.A. OralB. WrittenC. UpwardD. DownwardE. LateralANS: A24. On a precedence diagram, the arrow between
27、 two boxes is called:A. An activity.B. A constraint.C. An event.D. The critical path.E. None of above.ANS: B25. Quality control charts show a characteristic of the product or service against:A. the specification limits.B. customer requirements.C. control limits based on three standard deviations in
28、each direction.D. control limits based on six standard deviations in each direction.E. A and D onlyANS: C26. In the arrow diagramming method (ADM), _ do not consume time or resources.A. Events.B. Dummy ActivitiesC. Slack elements.D. B and C only.E. All of the above.ANS: A27. Activities with zero tim
29、e duration are referred to as:A. Critical path activites.B. Noncritical path activities.C. Slack time activities.D. DummiesE. None of above.ANS: D28. In the PDM, common constraints include:A. Start-to-startB. Finish-to-startC. Finish-to-finishD. B and C onlyE. A, B, and C.ANS: E29. Non-verbal commun
30、ication includes:A. Body movementB. GesturesC. Facial expressionsD. The way we move our handsE. All of the aboveANS: E30. Which one of the following is not an acquisition method?A. advertisingB. invitationC. negotiationD. purchaseE. all are acquisition methodsANS: A31. For communication to occur, th
31、ere must be:A. Two or more people involvedB. the transmittal of informationC. a communication processD. All of the aboveE. B and C onlyANS: D32. Job continuity would be an example of _ in Maslows hierarchy of needs.A. Self-actualizationB. EsteemC. PhysiologicalD. BelongingE. SafetyANS: E四、简单题(2*10=2
32、0 ) 。1. What are the major characteristics of a project? 项目的主要特点有哪些1).An established objective. 既定的目标2).A defined life span with a beginning and an end. 定义的寿命,有开始和结束3).Usually, the involvement of several departments and professionals. 通常情况下,几个部门及专业人士参与。4).Typically, doing something that has never be
33、en done before. 通常情况下,做一些从来没有过5).Specific time, cost, and performance requirements. 具体的时间、 成本和性能要求。2. What factors do you consider when choosing project management structure? At least five factors.选择项目管理结构时,你考虑什么因素?1).Size of project 项目的大小2).Strategic importance 战略重要性3).Novelty and need for innovati
34、on 新颖性和需要创新4).Number of departments involved 涉及多个部门5).Environmental complexity 环境的复杂性6).Budget and time constraints. 预算和时间限制7).Stability of resource requirement. 稳定的资源要求3. How to define the project? 如何定义项目?1).Defining the project scope 定义项目范围2).Establishing project priorities 建立项目优先事项3).Creating the
35、 work breakdown structure 创建工作分解结构4).Integrating the WBS with the organization 结合 WBS 组织5). Coding the WBS for the information system 编码为信息系统 WBS五、计算题(15*2=30 ) 。1.根据包装机制造项目的预算成本表和累计完成比率表,计算项目的表一 预算成本表周TBC1 2 3 4 5 6 7 8 9 10 11 12设计 30 10 15 5购买材料 70 10 20 20 20制造 40 5 10 10 10 5安装测试 30 10 20合计 170
36、 10 15 5 10 20 25 30 10 10 5 10 20表 2 包装机每期累计完成比率(%)周TBC1 2 3 4 5 6 7 8 9 10 11 12设计 25 60 80 100 100 100 100 100购买材料 10 35 60 80 100制造 10 40 40安装测试表 3 包装机累计挣值、CPI 和 CV周TBC1 2 3 4 5 6 7 8 9 10 11 12设计 30 7.5 18 24 30 30 30 30 30购买材料 70 7 24.5 42 56 70制造 40 4 16 24安装测试 30累计实际 CAC 8 20 26 36 53 78 110
37、 132累计挣值 CEV 7.5 18 24 37 54.5 76 102 118CPI 0.94 0.9 0.92 1.02 1.02 0.97 0.93 0.89CV -0.5 -2 -2 1 1.5 -2 -8 -142.求图中箭线图的关键路径。ES EF LS LF TSA 0 3 7 4 4B 0 5 5 0 0C 3 21 25 7 4D 5 12 12 5 0E 5 15 17 7 2F 12 17 17 12 0G 17 25 25 17 0H 25 27 27 25 0I 17 26 27 18 1J 17 22 24 19 2K 27 32 32 27 0L 22 30 32 24 2关键路径为:B-D-F-G-H-K