1、SH/T 3503-J503变 压 器 安 装 检 验 记 录Inspection Record of Transformer Installation 工程名称:Project:单元名称:Unit:Item No. DescriptionModel Rated capacity kVA ManufacturerRated voltage kV Cooling typeDate of Ex-workNameplateRated current A Total weight kg Serial No.Inspection items and requirements Result1 Centra
2、l line &elevation of body shall comply with design requirement.2 When transformer with wheel (without wheel) is put in place, it shall be fixed with a retainer (removable).3 Radiator shall be installed in compliance with technical requirement.4 All valves in oil line can be operated easily and are i
3、n correct opening or closed position, flanges are sealed without leakage.5 Oil reservoir shall be installed as per technical requirement, with correct oil level indication. 6 No crevice or abrasion on cleaned -up porcelain conduit surface. 7 Oil filled bushing shall be correctly mounted and sealed,
4、with correct oil level indication.8 Pressure relief valve shall be properly installed and wired.9 Burst pressure protective/relief device shall be correctly mounted.10 Pipeline of humidity absorption shall keep fluent with dry hygroscopic agent and properly oil sealed .11 Gas relay, thermometer shal
5、l be tested for qualification and correct mounting and wiring.12 Motor and blades of fan shall be firmly fixed, rotating easily without vibration and overheating.13 Electrical wiring shall be arranged in order and oil proofed, junction box must be properly sealed.14 Insulation oil shall be up to sta
6、ndard and filled in up to the specified level. 15 Earthing cable shall be in conformance to design and be connected firmly. 16 Tap switch is put in position of .17 Overall inspection of seals for leakage or seepage. Conclusion: Owner/Construction Supervision Contractor General Contractor Construction ContractorDiscipline engineer:Date: Discipline engineer:Date:Discipline engineer:Quality inspector:Construction foreman:Date: E.3 SH/T3503J503“变压器安装检验记录”用于电力变压器,也可用于变流、整流、电炉变压器。