1、SH/T 3503-J313釜类设备安装检验记录Kettle Type Equipment Installation Inspection Record工程名称:Project:单元名称:Unit:Description Item No.Item Allowable Value mm Actual ValuemmDeviation in Elevation of Kettle Body Deviation in Orientation of Kettle body 0/180 Deviation in Plumbness of Kettle body 90/2700/180Deviation
2、in Levelness of Top Opening Flange Face of Kettle Body 90/2700/180 Vertical Deviation of Stirrer Blade 90/270Deviation in Straightness of Stirrer Blade End Radial Displacement of Stirrer Blade Axial Movement of Stirrer Blade Radial Displacement of Stirrer Balde at Shaft SealConfirmation on Internal
3、Cleanness of Gear Box:Confirmation on Lube Oil System:Confirmation on Cooling System:Confirmation on Seal System:Inspection Conclusion:Owner/Supervision Contractor General Contractor Construction ContractorDiscipline engineer:Date:Discipline engineer:Date:Discipline engineer:Quality inspector:Construction foreman:Date: