1、SH/T 3503-J210水 池 蓄 水 试 验 记 录Water Basin Impoundment Test Record工程名称:Project:单元名称:Unit:Description Item No.Water Basin ConstructionAllowable Infiltration q0 L/m2dWater Basin Planar Size(LW ) m Water Area A1 m2Water Depth m Wet Area A2 m2Test Date: Started at and ended at Reading Record Initial Readi
2、ng Final Reading Reading DifferenceWater Level Reading E, mm E1 E2 E1E2Evaporation Water Basin Water Level Reading e, mm e1 e2 e1e2Water Temperature,Ambient Temperature,Reading-Taking Time (Minute, Hour, Date, Month)Actual Infiltration qq= A1 /A2( E1-E2) -( e1- e2) L/m2dPercentage of Actual Infiltra
3、tion to Allowable Infiltration q0 /q%Test Result:Owner/Supervision Contractor General Contractor Construction ContractorSH/T 35032007Discipline engineer:Date: Discipline engineer:Date: Discipline engineer:Quality inspector:Date:B.10 SH/T3503J210“水池蓄水试验记录”是依据 SH/T35352000石油化工混凝土水池工程施工及验收规范和 SH/T31322002石油化工钢筋混凝土水池结构设计规范的规定编制,通过测定相关的数据检验水池的工程质量状况。