1、DOCUMENT NUMBER AND REVISION:VL- PFMEAIZT2314-XX REV. ADOCUMENT TITLE :POTENTIAL FAILURE MODE AND EFFECTS ANALYSIS (PROCESS FMEA IZT2314-XX)OF LCM PRODUCTIONLCM 生產部潛在失效模式與效應分析(PFMEA IZT2314-XX)APPROVALS: EFFECTIVE DATE:DEPARTMENT部 門NAME姓 名SIGNATURE簽 名DATE日 期ORIGINATOR發 起 人 Li HaoPRODUCTION生 產 部QUALI
2、TY品 質 部ME制造工程部DESIGN 設計部DOCUMENT PAGE NO. 1 2 3 4REV A A A AAPPENDIX PAGE NO 1 2REV. A ADISTRIBUTION : PRODUCTION (LCM) QUALITY 分 發 : PROCESS (LCM) DESIGN (LCM) VL-PFMEA-IZT2314-XX REV.ADate: 2012/2/5PAGE 1 OF 4REVISIONFROM TO DATEREVISIONDESCRIPTIONCHANGEDBYCHECKEDBYA 2011/2/5 NEW DOCUMENT Li HaoVL
3、-PFMEA-IZT2314-XXREV. ADate: 2012/2/5PAGE: 2 OF 4CONTENTS:1.0 TITLE: Potential failure mode and effects analysis (PROCESS FMEA -IZT2314XX) of LCM production.2.0 PURPOSE: This document offers the assistance for engineer or production supervisor or related staff in process of analysis around potential
4、 failure modes and effects. And it (PFMEA) is the chief source of the drafting related control plan, in order to eliminate or reduce the chance of the potential failure occurring.3.0 SCOPE: This document is applicable to IZT2314-XX of LCM production in Varitronix Ltd.4.0 DEFINITION:N/A5.0 REFERENCE
5、DOCUMENT:5.1VL-PFMEA-003potential failure mode and effects analysis(Process FMEA- SMT) of LCM production5.2VL-PFMEA-007potential failure mode and effects analysis(Process FMEA-HEAT SEALING) of LCM production5.3VL-PFMEA-006potential failure mode and effects analysis(Process FMEA-Assembly) of LCM prod
6、uction 6.0 EQUIPMENT AND TOOLING:N/A7.0 MATERAIAL: N/AVL-PFMEA- IZT2314-XX REV. ADate: 2012/2/5PAGE 3 OF 48.0 RESPONSIBILITY:8.1 The engineers responsible for “MI” or “WI” should initiate these documents with reference of PFMEA. Especially, For the items with high risk priority number, The engineers
7、 responsible for “WI” or “MI” have responsibilities to point out corresponding actions in written description to avoid the potential failures.8.2 The ME engineers and supervisor responsible forIZT2238-XX project should monitor he process by the corresponding current process controls plan(s) of IZT22
8、38-XX PFMEA.9.0 TRAINING AND QUALIFICATION:Engineers who is assigned in the PFMEA of the IZT2238-XX project core team should be trained to the TS16949 requirements concerning about the PFMEA topic and should familiar in the PFMEA preparation (LCM) guided document (VL-PLM-037).10.0 PROCEDURE:10.1 As
9、some of the production requirements of the model IZT2238-XX product are different from the companys other products ,all the special individual PFMEA presented in the following appendix are applied in the subject model only .10.2 Refer to the appendix for the PFMEA applications and then implement the
10、 procedures stated in (VL-FMEA-002) .11.0 RECORD:N/A12. APPENDIX:12.1 APPENDIX 1,2,3PFMEA list of IZT2314-XX main process 12.2 APPENDIX 4PFMEA of TAB formingVL-PFMEA- IZT314-XX REV. ADate: 2012/2/5PAGE 4 OF 4PFMEA LIST OF IZT2314-XX MAIN PROCESSProcess Of IZT2314-XX(Flow Chart)RemarkN/ARefer to VL-P
11、FMEA-010A (APP1)Refer toAPP4Refer to VL-PFMEA-007 (APP7)Refer to VL-PFMEA-007 (APP6)N/ARefer to VL-PFMEA-007 (APP7)Refer to VL-PFMEA-007 (APP8)N/ARefer to PFMEA-006(APP20)Refer to PFMEA-006(APP6)Refer to VL-PFMEA-010A (APP1)Refer to PFMEA-006(APP6)VL-PFMEA- IZT2314-XXREV. CDate: 2012/2/5APPENDIX 1TA
12、B Forming FPC+ACF Attachment StartHS(TAB+ACF+FPC) DP190 dispensing HS(FPC+ACF+LCD) TAB+ACF Attachment Baking RTV dispensing& curingSemi testBakingInspection after HS Inspection after HS PFMEA LIST OF IZT2314-XX MAIN PROCESSProcess Of IZT2314-XX(Flow Chart)RemarkRefer to VL-PFMEA-006 (APP12)Refer to
13、VL-PFMEA -PST1-HYRefer to VL-PFMEA -ACL1-HYRefer to VL-PFMEA-003Refer to VL-PFMEA-007 (APP9)Refer to VL-PFMEA-006 (APP12)Refer to VL-PFMEA-006 (APP14)Refer to VL-PFMEA-006 (APP11)Refer to VL-PFMEA-006 (APP23,24)Refer to VL-PFMEA-006 (APP19)VL-PFMEA- IZT2314-XX REV.CDate: 2012/2/5APPENDIX 2Hot Bar (T
14、AB+PCA)LBL assembly & solderingBezel sticking gasketAssembly test & Black tape StickingInspection after Hot Bar& Reinforment tape stickingAssembly by lightSMTReinforcement tape stickingPolarizer stickingAutoclavePFMEA LIST OF IZT2311-XX MAIN PROCESSProcess Of IZT2314-XX(Flow Chart) N/A RemarkRefer to VL-PFMEA-006 (APP2)N/AN/ARefer to VL-PFMEA-006 (APP10)N/AN/AVL-PFMEA- IZT2314-XX REV. CDate: 2012/2/5APPENDIX 3Below Bezel Assembly and Bezel groundingShipmentOQA packing inspectionOQAPackingFinal test