1、Author:http:/ 肯德基门Document No.: 8474L -800 -17059 -6800- MS-005 A 1/6The Third Chemical Engineering Construction Company of China ( TCC)Author:http:/ 肯德基门VIETNAM OIL AND GAS CORPORATION (PETRO-VIETNAM)DUNG QUAT REFINERY (DQR) PROJECTMETHOD STATEMENT FORT1501S PIPE INSTALLATION Document No.:8474L-800

2、-17059-6800- MS005Rev. ADocument Class : ZREVIEW BY: TPC REVIEW BY PMC/DQRCODE 1 Revise and Resubmit CODE 1 Revise and ResubmitCODE 2 Review With Comments Work May Proceed/Revise first lifting higher position pipe line than lower;first lifting heavy pipe line than light,first lifting inside position

3、 pipe line than outside(east orientation is inside ),first installing pipe support than pipe,first pre-fabricationg pipe on the ground than install .this procedure is lifting the completely pipe line (A12-PG-150431-A2A5-NI),the pipe lines weight is about 22T,diameter is 48 inch,the install length is

4、 about 56m,from pipe top to bottom ,details please see attachment 2.Finish lifting this line,than lifting other lines.2、管道组对场地、堆放场地要求,见附图 3。Pipes are pre-fabrication on the ground,where are pipes placed ,please see attachment 3.3、管道吊装之前,该管线支架,按图施工完毕,特别是管线依附在塔上的支架必须施工完毕。管线吊装之前,塔顶平台必须安装完毕。All pipe sup

5、port should be installed prior to lifting thi pipe,especially on the T1501 bodys pipe support must be installed before lifting.The top platform of T1501 should be installed befor lifting pipe.4、吊装 A12-PG-150431-A2A5-NI 时,在高空中的工作采用从 T1501 顶部平台搭设脚手架平台进行高中作业。其余爬塔管线尽量采取先地面预制的方法,尽量减少高空作业。避免不了高空作业,利用塔平台或临

6、时施工平台配合进行施工作业。When lifting pipe line A12-PG-150431-A2A5-NI, scaffolding from the top platform of T1501,in order to assistant safety work in high air.All pipe line should most be pre-fabricationg on the ground,in order to reduce work in high air,when work must be in high air,scaffolding or temporary

7、platform is used to assistant installing work.5、管线仅考虑吊装到 HPP133838,以下为框架平台,管线比较容易安装。This procedure is only thinked about lifting which elevation is to HPP133838,below HPP133838 is structure and platform,all pipes are easy to install.6、吊装方法采用捆绑方法进行吊装。捆绑吊装点为该管线的重心点。重心位置详见附图 2。Binding method is used wh

8、en lifting pipe line,binding point is the gravity point.where is the gravity point of the pipe line,please see attachment 2.7、建议,吊装之前 T1501 北侧的钢结构框架暂时不要安装,等待 A12-PG-150431 管线吊装就位后安装,以免该管廊的安装会影响吊装 A12-PG-150431 管线。It recommended that the structure of North of T1501 cant be installed before installing

9、 the pipe line,after installing the pipe line A12-PG-150431 ,the structure is agreed to be installed,due to the structure is affect to lifting the pipe line.6. LIFTING STUDYAuthor:http:/ 肯德基门Document No.: 8474L -800 -17059 -6800- MS-005 A 5/6The Third Chemical Engineering Construction Company of Chi

10、na ( TCC)Author:http:/ 肯德基门本方案以整体吊装 A12-PG-150431-A2A5-NI 为主进行 LIFTING STUDY,其余管线比该线轻、小、底等,利用同一台吊车比较容易吊装。LIFTING STUDY 详见附件 4。This procedure is one time lifting on the right position when A12-PG-150431-A2A5-NI is completely pre-fabrication on the grond.So lifting study is about to total lift the pip

11、e line,other pipe line are light,small,lower etc,if use the same crane lifting them,it is very easier than this pipe line.please see attachment 4 :lifting study.7. HSE7.1 All workers involved in this project must wear proper PPE.7.2 AS Warning board or sign must be installed in dangerous area.7.3 Sp

12、ecial workers such as welders, electrician etc. must have required certificates.7.4 Different type of pressure bottles must be stored separately under shelter with correct secure accessories. Distance between different kinds of gas bottles shall not be less than 5m. Distance between oxygen bottle, a

13、cetylene bottle and flare shall be over 10m. And acetylene bottle must be placed vertically.7.5 Construction power and electrical tools and equipment must be arranged according to specification. At least 2 grounding points to be installed for steel platform, cable for welding must be check in period

14、 and replace damaged portion.7.6 During lifting, operator of cranes and riggers must have good coordination, and operators shall operate crane in command of signal from riggers. Riggers shall signal operator with gesture and whist. And operator can reject unclear signal from rigger. Lifting area mus

15、t be barricaded, and keep persons not involve in lifting away. Signalman shall wear the HIVIZ vest.7.7 During lifting, it is forbidden to stay or walk under suspended area.7.8 During lifting, speed of taking up and lowing lifted piece shall be smooth. Swing of boom shall be smooth, and reverse actio

16、n cannot be done while swing not stopped. It is forbidden to let lift hook with load fall down freely. Use tag lines to control load. 7.9 Tools and accessories must be put in bags for elevation work. It is forbidden to throw object from high place. 7.10 Lifting study and permit to work must be appro

17、ved by TPC prior to lifting work.8. JOB SAFETY ANALYSISPlease refer to Attachment-029. WORKING MACHINE PLANNo Name spec model unit quantity remark1 Crawl crane 250t piece 12 Truck crane 50t piece 13 PWHT manchine piece 14 welding machine piece 4Author:http:/ 肯德基门Document No.: 8474L -800 -17059 -6800

18、- MS-005 A 6/6The Third Chemical Engineering Construction Company of China ( TCC)Author:http:/ 肯德基门5 Dry oven piece 16 grinding machine piece 107 theodolite piece 18 water level piece 19 tape 30m piece 110 tape 10m piece 211 tape 5m piece 512 heat preservation canisterpiece 410. THE ASSISTANT MATERI

19、AL LIST TABLENo Name spec model unit quantityremark1 Lifting belt 20t pieces 1 Or wire rope2 block 2T piece 4 Assistant of lifting3 crosstie 1602203000 piece 40 support equipment4 PIPE 48*3.5 T 1 scaffolds5 others T 2 Steel plate etc11. manpower planSite Mgr 1 people technician 1peopleHSSE Mgr 1 people pipe enginer 1peopleMaterial Mgr 1 people Keeper 1 people electrician 1 people welding worker 4 peoplelifting worker 4 people scaffold worker 2 peoplelaborer 8 people pipe worker 8 people