1、 CHAWR Quote No.:CRQ-10-0012 Rev10Aug.30,10Attn: 赵一宁 小姐W.E.T Automptive Systems (China) Ltd. (威意特汽车系统(中国)有限公司)河北省廊坊经济技术开发区金源道 3 号Tel: +86-0316-6071100-251Fax: +86-0316-6071260Hp: E-mail: Grace.zhaowet-Subject: Quotation for 压合机设备复制Quote No.: CRQ-10-0012 Rev1.0Dear Ms. Grace,Thank you very much for y
2、our inquiry. we are great pleased to get this opportunity to show our knowledge and capability to you personal and your corporation. Your quotation request is for a 压合机设备复制, it is just covered by our business area and we have a lot of similar experience to design, build such a machine.非常感谢您的垂询。我们非常高
3、兴能够有机会把我们的专业技能展现给您和贵公司。您的报价需求是“压合机设备复制” ,这个项目正好在我们的商业范围内,我们有很多类似的经验去设计、制造这样的设备。This project is based on design, manufacture and integrates at Tianjin Chawr Automation Technologies. Tianjin Chawr will also provide service support.本工程将由天津超尔自动化技术有限公司进行设计、制造,并在天津超尔进行组装及调试。天津超尔自动化技术有限公司 进行各项售后服务Thank you
4、 for the opportunity to submit this proposal and we look forward to being of service.感谢能有为您提供方案的机会,期待您的回复-i-Your Sincerely顺颂商祺!- Sun Jingquan孙景泉Sales ManagerMobile: 13820963714E-mail: -Shao Yu邵 宇Technology DirectorMobile: 13820936823E-mail: Tianjin Chawr Automation Technologies Co., Ltd.天津超尔自动化技术有限公
5、司-ii-A quotation for威意特汽车系统(中国)有限公司压合机设备复制Quote No.: CRQ-10-0012 Rev1.0Aug. 30, 10Tianjin Chawr Automation Technologies Co., Ltd. This quotation is a confidential document that contains proprietary information, and is protected by copyright. The quotation remains the property of Chawr at all times.
6、Unauthorized reproduction of this document, or transmission of the information in the document to third parties, is strictly prohibited without the express written approval of Chawr.Quotation number 报价单号: CRQ-10-0012Rev1.0 Created by 编制:Shao Yu -1-List of changes 变更记录No.序号Date日期Revision版本Reason for
7、change更改理由Rev.by变更人1 2010-8-25 Rev0.0 First issue Shao YuQuotation number 报价单号:CRQ-10-0012 Rev1.0 Created by 编制:Shao Yu -2-Table of Contents 目录Executive Summary 概要-4 System Pricing 系统价格-5Delivery and Sales Terms 供货及基本条款-6System Description and List of Deliverables 工程描述及交货明细-8Project Management 工程管理-
8、9Project Implementation 工程进程-10CHAWR Conditions of Sale 超尔商务准则-11List of attached filed 附件清单Quotation number 报价单号:CRQ-10-0012 Rev1.0 Created by 编制:Shao Yu -3-Executive Summary 概要This protocol has been prepared in response to W.E.T Automptive Systems (China) Ltds require for a quotation to design and
9、 build up for 压合机设备复制.本方案为我公司应威意特汽车系统(中国)有限公司对设计并制造压合机设备复制进行报价的要求,而精心准备的。The system will be designed to meet the following basic requirements of W.E.T Automptive Systems (China) Ltd.系统将按威意特汽车系统(中国)有限公司的“压合机设备复制”技术要求进行设计Reference drawings,specifications etc. of customer are detailed as follows,客户提供的资
10、料如下:序号 名称 技术要求1 复制布线机业务要求 按现有布线机设备进行改复制,技术要求详见“复制布线机业务要求”注:1 超尔公司按照威意特公司提供的“电气接线图” 、 “气动原理图” 、 “控制系统零配件列表(spare parts list) ”进行布线机设备复制,超尔公司不负责应用程序设计及录入2,以下报价不含 PANEL 上的 Working Screen MAC E300 和 电源箱中的 ESGT-1ph (PCB) 组件。需要和 WET 技术人员进一步确认!3“控制系统零配件列表(spare parts list) ”如果与现有旧设备实际的电器元器件及数量不符,则超尔公司按照实际需
11、要增加相应部分报价4,对于交货期比较长的电气元件,超尔可以采用其它质量品牌的元件。Quotation number 报价单号:CRQ-10-0012 Rev1.0 Created by 编制:Shao Yu -4-System Pricing 系统价格Subject: 压合机设备复制压合机设备复制S/N Description Qty Unit Price Amount1 框架、台面及附件 1 9800 98002 气动组件(Festo):(包括压装气缸)1 个,气源组件1 个,压线气缸 6 个,顶起气缸 8,输送气缸 2 个,2 位 3 通电磁阀 2个,行程开关 2 个,手动开关 4 个,气
12、控阀、节流阀、消音器、等其它气动附件)1 41780 417803 电气组件“控制系统零配件列表(spare parts list) ”1 53755 537554 机械加工件(上顶板+下压板+加热板+导向轴+垫板+连接件+ 支架等)1 37950 379505 直线轴承 4 个(输送气缸) 、导轨、气缸导向块、导向支撑块等1 6760 67606 直线轴承(下压汽缸工位) 1 700 7007 防护罩 1 500 5008 其它附件 1 3240 3240机械设计 4300电气硬件 2000机械装配 1500电气装配 860调试 1630预验收 0文档 200培训 0管理费用 200利润 6
13、380客户端安装调试及验收 2670运输及保险 1300Total Price before VAT 175525VAT 29839Total System Price After VAT 205364Quotation number 报价单号:CRQ-10-0012 Rev1.0 Created by 编制:Shao Yu -5-Delivery and Sales Terms 供货及基本条款Lead Time 供货期The lead time for shipping out of project from CHAWR plant at 29th Oct,2010.based on rec
14、eipt of a written purchase order and down payment.生产线的发货日期为2010年10月29日。起始日期根据合同生效日期及首付款到位情况而定。A detailed schedule for designing, building up the machine, commissioning and setting up of theproject can be provided by CHAWR. However the timeline can not be granted as a promise andis subjected to chang
15、e according to the project proceeding actual status or public long holidaysetc.超尔可提供关于项目设计、制造、交付及投产的详细工程进度表,进度表所列日期仅为参考不可视为我司的承诺且可能会根据项目实施的具体情况及公共长假的影响等适当调整。A promised lead time is upon receipt of a written purchase order供货期的保证将由以下条款作为基础: 收到有效合同及定单Failure by the customer to provide this information
16、with or prior to, the written purchase ordermay result in a delay of the original project schedule. CHAWR. is not responsible for anydelay caused by failure to provide this information.以上条款尤其是正式订单签发的延误将有可能影响交货日期,超尔将不能为此负责。Payment Terms 付款方式 30 % down payment within 3 days after the formal PO issued签
17、订正式订单3 日内预付总价格的30%的预定金。 70% within 7 days after final acceptance of machine.总价格的70%将在终验收合格后7 天内支付。Quotation number 报价单号:CRQ-10-0012 Rev1.0 Created by 编制:Shao Yu -6-Additional Terms 其他条款 This quotation is valid for 60 days. 本报价的有效期为60 天 The customer purchase order must refer to quotation number CRQ-1
18、0-0012 Rev1.0,andthey are can not be divided. 本报价单CRQ-10-0012 Rev1.0 将作为日后正式定货合同及定单不可分割部分。 Delivery Point: Buyer plant 收货地点:买方工厂 All prices are quoted in RMB Funds. 本报价以人民币结算 Subject to CHAWR Conditions of Sale (attached below). 本报价遵循超尔商务条款(附后)Standard Warranty Period 保修期CHAWR warrants that the part
19、s manufactured and software produced by them will be freefrom defects in workmanship and material for a period of 18 months超尔将对所提供的新的零部件,标准件及控制程序提供1 年半保修。Quotation number 报价单号:CRQ-10-0012 Rev1.0 Created by 编制:Shao Yu -7-System Description and List of Deliverables 工程描述及交货明细The following is a brief op
20、erational description of the assembly system including a list of themajor component deliverables at each tool. Unless otherwise noted all deliverables are inquantities of one (1).以下为系统的简要描述,和主要零部件的交货明细,除特别注明外,其数量为1 件。System main character, performance or parameter 系统主要特征,特性及参数Subject: 压合机设备复制压合机设备复制
21、Deliverables(超尔提供)1 框架、台面(实木)及附件2 气动组件(Festo):(包括压装气缸)1 个,气源组件 1 个,压线气缸 2 个,顶起气缸 4,输送气缸 2 个,2 位 3 通电磁阀 2 个,行程开关 2 个,手动开关 4 个,气控阀、节流阀、消音器、等其它气动附件)3 电气组件“控制系统零配件列表(spare parts list) ”4 机械加工件(上顶板+下压板+加热板+ 导向轴+垫板+连接件+支架等)5 导轨、气缸导向块、导向支撑块等6 直线轴承7 防护罩8 其它附件Quotation number 报价单号:CRQ-10-0012 Rev1.0 Created
22、by 编制:Shao Yu -8-General System Deliverables 系统常规交付清单The following items are included with any CHAWR system provided. 以下各项包含在超尔所交付的系统中 Floor assembly and integration 现场安装,调试,集成 Project management 项目管理 Operations and Maintenance Manuals 操作及维修服务手册 Training 培训Project Management 工程管理To be successful, al
23、l projects require a great deal of coordination and communication between the supplier and the customer. The communicationmust be timely and accurate in order to ensure successful completion and on-time delivery of the system.To meet these requirements, CHAWR assigns a Project Manager to coordinate
24、the design and build effort at CHAWR as well as being thefocal point for all communications with the customer.Role of the CHAWR Project ManagerThe CHAWR Project Manager performs the following functions: Provides a single point contact for the customer Distributes information to the CHAWR project tea
25、m members Provides objectives and priorities to the CHAWR project team members Coordinates design reviews and critical design review meetings with the customer Monitors the status of the project and provides regular status reports to the customer Processes changes to the contractProject Reporting to
26、 the CustomerProject reporting to the customer is handled through a number of channels. In addition to verbal reports, the CHAWR Project Manager canalso provide bi-weekly written reports on project status. Typically, the written report includes the following items: An updated project task schedule D
27、esign review status Manufacturing status Delivery status of major hardware purchases Floor assembly and integration status Outstanding action items Contract changes (CORs)It is also expected that during the course of the project, members of the CHAWR and customer project teams meet on a regular basi
28、s (at leastmonthly) to review project progress, to resolve any outstanding technical or schedule issues and to set priorities for the project team.Following these meetings, minutes are issued by the project manager outlining the following: Outstanding items - Issues which require resolution, whom th
29、e action is charged to and when it is due. Closed items - Issues which have been determined closed and are now no longer open for discussion General progress - Events which have transpired within the last weekProject Planning and Resource AllocationRD-TECH employs the project planning and control sy
30、stem. All of the active jobs in-house are accounted for in this system providing anaccurate resource loading plan that is then issued to the production departments.Bi-weekly schedules are issued for projects in production identifying critical paths and highlighting resource constraints. Project sche
31、dules areupdated based on data from several sources: the Project Managers input regularly review the progress on the project with the department managersQuotation number 报价单号:CRQ-10-0012 Rev1.0 Created by 编制:Shao Yu -9- monitors the delivery status of major hardware items design releases to the shop
32、 reported completion of assemblies in the shop regular review of floor statusWhile CHAWR in-house production planning and control accommodates all jobs, the Project Manager is specifically responsible for the projectwhile it is in each phase of design and production. This system allows potential pro
33、blems to be identified early, before they become an issue.Engineering Change Notice and ProcedureIn order to manage and record changes to the project design and/or changes to the scope of work CHAWR utilizes a formal Engineering ChangeNotice (ECN) Procedure.The changes are recorded on a Change Order
34、 Request (COR) form which can be initiated by the CHAWR Project Manager or the customersProject Manager. The description section of the form is completed and submitted to the CHAWR Operations Manager for assessment of thecost, delivery and performance impacts on the system.After these impacts are as
35、sessed, the COR is submitted for customer approval. After approval, the signed COR is returned to CHAWR and thechanges outlined are implemented. The customer is then requested to submit a modified purchase order to reflect these changes.This procedure keeps both CHAWR and the customer fully aware of
36、 the cost and delivery status of the project as well as providing a method oftracking and recording all changes to the original scope of work.Project Implementation 工程进程The implementation of projects at CHAWR is broken into six phases. At the completion of each phase, members of the CHAWR andcustome
37、r project teams meet to resolve technical and schedule issues. During each phase, the project specification and supporting qualitydocumentation are revised to reflect project status.Mechanical and Electrical DesignThe mechanical and electrical design phases of the project run concurrently. Following
38、 the receipt of customer component drawings andsamples and the production of a final system layout, work can begin on individual cell and stations layouts. Mechanical assembly drawings areproduced for all stations to illustrate the proposed assembly concept.Following customer approval, the major ass
39、emblies are detailed and drawings are released for production. Prototypes of new mechanisms mayalso be built during this time to verify design concepts.During the electrical design phase of the project, the controls architecture, controls hardware and desired functionality of the system are finalize
40、d.Based on the station I/O and power requirements, panel layouts are developed to house all of the required controls hardware.Safety circuits and operator controls are also designed during this phase of the project. Following customer design approval, the electricaldesign package is released for pro
41、duction.System FabricationThe bulk of the mechanical and electrical details are built and installed on the system during the tooling build phase. At the completion of thisphase, the system appears almost complete but is not yet fully functional.Safety guarding and a few long lead items are usually n
42、ot in place at this time. Although mechanically complete, the programming is not yetimplemented at this stage.Integration and DebugDuring this phase of the project, the software to control the machine is installed and the mechanical devices are cycled. This process beginswith the debug of individual
43、 stations and proceeds until the whole system is functional.Once the system has achieved a certain level of reliability and is producing accepable parts, a pre-acceptance checklist is filled out. If themachine meets all the conditions on the checklist, the customer is invited for formal acceptance o
44、f the machine.Customer Acceptance and ShipmentThere will be the customer present to verify that it meets the design specifications at CHAWR site. After the machine is assembled and run-offat CHAWR site, it is dis-assembled, packed and shipped to the customers facility.Quotation number 报价单号:CRQ-10-00
45、12 Rev1.0 Created by 编制:Shao Yu -10-Site InstallationInstallation of this system is performed by CHAWR personnel. The installation price quoted in this proposal is based on the followingbreak-down of responsibilities: Customer personnel will knock down shipping crates and discard all packing materia
46、ls. The customer supplys lift trucks to move equipment from crates to the proper location within the plant. The customer installs all utility drops to the equipment. RD-TECH will spot, level, lag and align all stations, connect all electrical and pneumatic interconnections and commission the entires
47、ystem.Final AcceptanceOnce the system has been installed in the customers facility a final acceptance procedure is run. This procedure again verifies that the systemmeets the design specifications for the system.CHAWR Conditions of Sale 超尔商务准则1. Orders cancelled in written by the customer at any time prior to the delivery date are subject to accrued charges for engineering, labor andmaterial. 在供货期之前的任何时间,客户可根据自己的需要以文字形式通知供方取消合同, 但此前所产生的一切工程费用,劳动力和材料费用由客户承担.2. Purchased items suc