1、项目名称 日期BIM 项目实施指南 iBIM 项目实施计划书项目名称陕西建工集团总公司目录第一章: 概述 1第二章: 项目信息 .2第三章: 重要项目成员的联系方式 3第四章: 项目目标/BIM 应用 .4第五章: 组织角色/人员配备 .5第六章: BIM 实施流程设计 6第七章: BIM 信息交换 .7第八章: BIM 和设备信息需求(甲方) 8第九章: 协作流程 .9第十章: 质量控制 .11第十一章: 技术方面的配套设施要求 12第十二章: 模型架构 .13第十三章: 项目交付 .14第十四章: 交付策略 / 合同 .15第十五章: 附件 16项目名称 日期BIM 项目实施指南 1第一章
2、: 概述To successfully implement Building Information Modeling (BIM) on a project, the project team has developed this detailed BIM Project Execution Plan. The BIM Project Execution Plan defines uses for BIM on the project (e.g. design authoring, cost estimating, and design coordination), along with a
3、detailed design of the process for executing BIM throughout the project lifecycle. INSERT ADDITIONAL INFORMATION HERE IF APPLICABLE. FOR EXAMPLE: BIM MISSION STATEMENT This is the location to provide additional BIM overview information. Additional detailed information can be included as an attachmen
4、t to this document.Please note: Instructions and examples to assist with the completion of this guide are currently in grey. The text can and should be modified to suit the needs of the organization filling out the template. If modified, the format of the text should be changed to match the rest of
5、the document. This can be completed, in most cases, by selecting the normal style in the template styles.项目名称 日期BIM 项目实施指南 2第二章: 项目信息This section defines basic project reference information and determined project milestones.1. PROJECT OWNER:2. PROJECT NAME:3. PROJECT LOCATION AND ADDRESS:4. CONTRACT
6、 TYPE / DELIVERY METHOD:5. BRIEF PROJECT DESCRIPTION: NUMBER OF FACILITIES, GENERAL SIZE, ETC6. ADDITIONAL PROJECT INFORMATION: UNIQUE BIM PROJECT CHARACTERISTICS AND REQUIREMENTS7. PROJECT NUMBERS:PROJECT INFORMATION NUMBERCONTRACT NUMBER:TASK ORDER:PROJECT NUMBER:8. PROJECT SCHEDULE / PHASES / MIL
7、ESTONES:Include BIM milestones, pre-design activities, major design reviews, stakeholder reviews, and any other major events which occur during the project lifecycle. PROJECT PHASE / MILESTONE ESTIMATED START DATEESTIMATED COMPLETION DATEPROJECT STAKEHOLDERS INVOLVEDPRELIMINARY PLANNINGDESIGN DOCUME
8、NTSCONSTRUCTION DOCUMENTSCONSTRUCTION项目名称 日期BIM 项目实施指南 3第三章: 重要项目成员的联系方式List of lead BIM contacts for each organization on the project. Additional contacts can be included later in the document.ROLE ORGANIZATION CONTACT NAME LOCATION E-MAIL PHONEProject Manager(s)BIM Manager(s)Discipline LeadsOther
9、Project Roles项目名称 日期BIM 项目实施指南 4第四章: 项目目标/BIM 应用Describe how the BIM Model and Facility Data are leveraged to maximize project value (e.g. design alternatives, life-cycle analysis, scheduling, estimating, material selection, pre-fabrication opportunities, site placement, etc.) Reference www.engr.psu
10、.edu/bim/download for BIM Goal & Use Analysis Worksheet.1. MAJOR BIM GOALS / OBJECTIVES: State Major BIM Goals and ObjectivesPRIORITY(HIGH/ MED/ LOW)GOAL DESCRIPTION POTENTIAL BIM USES2. BIM USE ANALYSIS WORKSHEET: ATTACHMENT 1Reference www.engr.psu.edu/bim/download for BIM Goal & Use Analysis Works
11、heet. Attach BIM Use analysis Worksheet as Attachment 1.3. BIM USES: Highlight and place an X next to the additional BIM Uses to be developed by the use of the BIM model as selected by the project team using the BIM Goal & Use Analysis Worksheet. See BIM Project Execution Planning Guide at www.engr.
12、psu.edu/BIM/BIM_Uses for Use descriptions. Include additional BIM Uses as applicable in empty cells.X PLAN X DESIGN X CONSTRUCT X OPERATEPROGRAMMING DESIGN AUTHORING SITE UTILIZATION PLANNING BUILDING MAINTENANCE SCHEDULINGSITE ANALYSIS DESIGN REVIEWS CONSTRUCTION SYSTEM DESIGN BUILDING SYSTEM ANALY
13、SIS3D COORDINATION 3D COORDINATION ASSET MANAGEMENTSTRUCTURAL ANALYSIS DIGITAL FABRICATION SPACE MANAGEMENT / TRACKINGLIGHTING ANALYSIS 3D CONTROL AND PLANNING DISASTER PLANNINGENERGY ANALYSIS RECORD MODELING RECORD MODELINGMECHANICAL ANALYSISOTHER ENG. ANALYSISSUSTAINABLITY (LEED) EVALUATIONCODE VA
14、LIDATIONPHASE PLANNING(4D MODELING)PHASE PLANNING(4D MODELING)PHASE PLANNING(4D MODELING)PHASE PLANNING(4D MODELING)COST ESTIMATION COST ESTIMATION COST ESTIMATION COST ESTIMATIONEXISTING CONDITIONS MODELINGEXISTING CONDITIONS MODELINGEXISTING CONDITIONS MODELINGEXISTING CONDITIONS MODELING项目名称 日期BI
15、M 项目实施指南 5第五章: 组织角色/人员配备Determine the projects BIM Roles/Responsibilities and BIM Use Staffing1. BIM ROLES AND RESPONSIBILITIES: Describe BIM roles and responsibilities such as BIM Managers, Project Managers, Draftspersons, etc.2. BIM USE STAFFING: For each BIM Use selected, identify the team within
16、 the organization (or organizations) who will staff and perform that Use and estimate the personal time required.BIM USE ORGANIZATION NUMBER OF TOTAL STAFF FOR BIM USE ESTIMATED WORKER HOURS LOCATION(S) LEAD CONTACT3D coordination Contractor ABC项目名称 日期BIM 项目实施指南 6第六章: BIM 实施流程设计Provide process maps
17、for each BIM Use selected in section D: Project Goals/BIM Objectives. These process maps provide a detailed plan for execution of each BIM Use. They also define the specific Information Exchanges for each activity, building the foundation for the entire execution plan. The plan includes the Overview
18、 Map (Level 1) of the BIM Uses, a Detailed Map of each BIM Use (Level 2), and a description of elements on each map, as appropriate. Level 1 and 2 sample maps are available for download at www.engr.psu.edu/BIM/download. (Please note that these are sample maps and should be modified based on project
19、specific information and requirements). Please reference Chapter Three: Designing BIM Project Execution Process in the BIM Project Execution Planning Guide found at www.engr.psu.edu/BIM/PxP 1. LEVEL ONE PROCESS OVERVIEW MAP: ATTACHMENT 22. LIST OF LEVEL TWO DETAILED BIM USE PROCESS MAP(S): ATTACHMEN
20、T 3The following are examples. Modify for specific project. Some Process Maps may need to be removed, while some process maps may need to be added.a. Existing Conditions Modelingb. Cost Estimationc. Phase Planning (4D Modeling)d. Programminge. Site Analysisf. Design Reviewsg. Design Authoringh. Ener
21、gy Analysisi. Structural Analysisj. Lighting Analysisk. 3D Coordinationl. Site Utilization Planningm. 3D Control and Planningn. Record Modelingo. Maintenance Schedulingp. Building System AnalysisDelete unused or add additional process maps from list项目名称 日期BIM 项目实施指南 7第七章: BIM 信息交换Model elements by d
22、iscipline, level of detail, and any specific attributes important to the project are documented using information exchange worksheet. See Chapter Four: Defining the Requirements for Information Exchanges in the BIM Project Execution Planning Guide for details on completing this template. 1. LIST OF
23、INFORMATION EXCHANGE WORKSHEET(S): ATTACHMENT 4The following are examples. Modify for specific project. Some Information Exchanges may need to be removed, while some Information Exchanges may need to be added. a. Existing Conditions Modelingb. Cost Estimationc. Phase Planning (4D Modeling)d. Program
24、minge. Site Analysisf. Design Reviewsg. Design Authoringh. Energy Analysisi. Structural Analysisj. Lighting Analysisk. 3D Coordinationl. Site Utilization Planningm. 3D Control and Planningn. Record Modelingo. Maintenance Schedulingp. Building System Analysisq. Delete unused information exchanges fro
25、m list 2. MODEL DEFINITION WORKSHEET: ATTACHMENT 5(Attach Model Definition Worksheet)项目名称 日期BIM 项目实施指南 8第八章: BIM 和设备信息需求(甲方)The section should include the owners BIM requirements. It is important that the owners requirements for BIM be considered so that they can be incorporated into the projects BI
26、M process. 项目名称 日期BIM 项目实施指南 9第九章: 协作流程1. COLLABORATION STRATEGY:Describe how the project team will collaborate. Include items such as communication methods, document management and transfer, and record storage, etc. 2. MEETING PROCEDURES: The following are examples of meetings that should be consid
27、ered.MEETING TYPE PROJECT STAGE FREQUENCY PARTICIPANTS LOCATIONBIM REQUIREMENTS KICK-OFFBIM EXECUTION PLAN DEMONSTRATIONDESIGN COORDINATION CONSTRUCTION OVER-THE-SHOULDER PROGRESS REVIEWSANY OTHER BIM MEETINGS THAT OCCURS WITH MULTIPLE PARTIES3. MODEL DELIVERY SCHEDULE OF INFORMATION EXCHANGE FOR SU
28、BMISSION AND APPROVAL:Document the information exchanges and file transfers that will occur on the project. INFORMATION EXCHANGE FILESENDER FILERECEIVER ONE-TIME or FREQUENCYDUE DATE or START DATEMODEL FILEMODEL SOFTWARENATIVE FILE TYPEFILE EXCHANGE TYPEDESIGN AUTHORING - 3D COORDINATION STRUCTURAL
29、ENGINEER(FTP POST)(COORDINATION LEAD)WEEKLY DATE STRUCT DESIGN APP .XYZ .XYZ.ABCMECHANICAL ENGINEER(FTP POST)(COORDINATION LEAD)WEEKLY DATE MECH DESIGN APP .XYZ .XYZ.ABC4. INTERACTIVE WORKSPACEThe project team should consider the physical environment it will need throughout the lifecycle of the proj
30、ect to accommodate the necessary collaboration, communication, and reviews that will improve the BIM Plan decision making process. Describe how the project team will be located. Consider questions like “will the team be collocated?” If so, where is the location and what will be in that space? Will t
31、here be a BIM Trailer? If yes, where will it be located and what will be in the space such as computers, projectors, tables, table configuration? Include any additional information necessary information about workspaces on the project.项目名称 日期BIM 项目实施指南 105. ELECTRONIC COMMUNICATION PROCEDURES:(Note:
32、 File Naming and Folder Structure will be discussed in Section L: Model Structure).The following document management issues should be resolved and a procedure should be defined for each: Permissions / access, File Locations, FTP Site Location(s), File Transfer Protocol, File / Folder Maintenance, et
33、c.FILE LOCATION FILE STRUCTURE / NAME FILE TYPE PASSWORD PROTECTFILEMAINTAINERUPDATEDFTP SITE:ftp:/ftp.*.com/*/*ROOT PROJECT FOLDER FOLDERYES*JIM McBIM ONCEARCH ROOT FOLDER FOLDER ONCEARCH-11111-BL001.xyz .xyz DAILYNETWORK drive PSUF:PROJECTBIMROOT PROJECT FOLDER FOLDER NO JIM McBIM ONCEProject Mana
34、gement Softwarewww.*.com项目名称 日期BIM 项目实施指南 11第十章: 质量控制1. OVERALL STRATEGY FOR QUALITY CONTROL:Describe the strategy to control the quality of the model.2. QUALITY CONTROL CHECKS:The following checks should be performed to assure quality.CHECKS DEFINITION RESPONSIBLE PARTY SOFTWARE PROGRAM(S) FREQUENC
35、Y VISUAL CHECKEnsure there are no unintended model components and the design intent has been followedINTERFERENCE CHECKDetect problems in the model where two building components are clashing including soft and hardSTANDARDS CHECKEnsure that the BIM and AEC CADD Standard have been followed (fonts, di
36、mensions, line styles, levels/layers, etc)MODEL INTEGRITY CHECKSDescribe the QC validation process used to ensure that the Project Facility Data set has no undefined, incorrectly defined or duplicated elements and the reporting process on non-compliant elements and corrective action plans3. MODEL AC
37、CURACY AND TOLERANCES:Models should include all appropriate dimensioning as needed for design intent, analysis, and construction. Level of detail and included model elements are provided in the Information Exchange Worksheet. PHASE DISCIPLINE TOLERANCEDESIGN DOCUMENTS ARCH ACCURATE TO +/- # OF ACTUA
38、L SIZE AND LOCATIONSHOP DRAWINGS MECH CONTRACTOR ACCURATE TO +/- # OF ACTUAL SIZE AND LOCATION项目名称 日期BIM 项目实施指南 12第十一章: 技术方面的配套设施要求1. SOFTWARE:List software used to deliver BIM. Remove software that is not applicable.BIM USE DISCIPLINE(if applicable) SOFTWARE VERSIONDESIGN AUTHORING ARCH XYZ DESIGN
39、APPLICATION VER. X.X (YEAR)2. COMPUTERS / HARDWARE:Understand hardware specification becomes valuable once information begins to be shared between several disciplines or organizations. It also becomes valuable to ensure that the downstream hardware is not less powerful than the hardware used to crea
40、te the information. In order to ensure that this does not happen, choose the hardware that is in the highest demand and most appropriate for the majority of BIM Uses. BIM USE HARDWARE OWNER OF HARDWARE SPECIFICATIONSDESIGN AUTHORING XXX COMPUTER SYSTEM ARCHITECT XPROCESSOR, OPERATING SYSTEM, MEMORY
41、STORAGE, GRAPHICS, NETWORK CARD, ETC.3. MODELING CONTENT AND REFERENCE INFORMATIONIdentify items such as families, workspaces, and databases. BIM USE DISCIPLINE(if applicable) MODELING CONTENT /REFERENCE INFORMATION VERSIONDESIGN AUTHORING ARCH XYZ APP FAMILIES VER. X.X. (YEAR)ESTIMATING CONTRACTOR
42、PROPRIETARY DATABASE VER. X.X (YEAR)项目名称 日期BIM 项目实施指南 13第十二章: 模型架构1. FILE NAMING STRUCTURE:Determine and list the structure for model file names. FILE NAMES FOR MODELS SHOULD BE FORMATTED AS:DISCIPLINE - PROJECT NUMBER BUILDING NUMBER.XYZ (example: ARCH-11111-BL001.xyz)ARCHITECTURAL MODEL ARCH- CIVI
43、L MODEL CIVIL- MECHANICAL MODEL MECH-PLUMBING MODEL PLUMB-ELECTRICAL MODEL ELEC-STRUCTURAL MODEL STRUCT-ENERGY MODEL ENERGY-CONSTRUCTION MODEL CONST-COORDINATION MODEL COORD-2. MODEL STRUCTURE:Describe and diagram how the Model is separated, e.g., by building, by floors, by zone, by areas, and/or di
44、scipline. 3. MEASUREMENT AND COORDINATE SYSTEMS:Describe the measurement system (Imperial or Metric) and coordinate system (geo-referenced) used.4. BIM AND CAD STANDARDS:Identify items such as the BIM and CAD standards, content reference information, and the version of IFC, etc.STANDARD VERSION BIM
45、USES APLICABLE ORGANIZATIONS APLICABLECAD STANDARD DESIGN AUTHORING ARCHITECTIFC VERSION/MVD(s) RECORD MODELING CONSTRUTION MANAGER项目名称 日期BIM 项目实施指南 14第十三章: 项目交付In this section, list the BIM deliverables for the project and the format in which the information will be delivered. BIM SUBMITTAL ITEM ST
46、AGE APPROXIMATE DUE DATE FORMAT NOTESDesign DevelopmentConstructionDocumentsConstructionRecord Model Close out (.xyz)See Record Model Information Exchange to ensure that the proper information is contained in this model项目名称 日期BIM 项目实施指南 15第十四章: 交付策略 / 合同1. DELIVERY AND CONTRACTING STRATEGY FOR THE P
47、ROJECT:What additional measures need to be taken to successfully use BIM with the selected delivery method and contract type?2. TEAM SELECTION PROCEDURE:How will you select future team members in regards to the above delivery strategy and contract type?3. BIM CONTRACTING PROCEDURE: How should BIM be
48、 written into the future contracts? (If documents / contracts are developed, please attach as attachment 6)项目名称 日期BIM 项目实施指南 16第十五章: 附件1. BIM USE SELECTION WORKSHEET FROM SECTION D2. LEVEL 1 PROCESS OVERVIEW MAP FROM SECTION F3. LEVEL 2 DETAILED BIM USE PROCESS MAP(S) FROM SECTION F4. INFORMATION EXCHANGE REQUIREMENT WORKSHEET(S) FROM SECTION G5. MODEL DEFINITION WORKSHEET FROM SECTION G6. DEVELOPED DOCUMENTS / CONTRACTS FROM SECTION H